Buying
Do you need a certificate of occupancy to close on a new home in Texas?
November 20, 2026 · By Kenny Agbim · 6 min read
Texas has no statewide certificate of occupancy, so the answer is set city by city. Plano's own guide says certificates are not issued for single-family homes. Dallas's development code applies except for single family and duplex uses, yet the city still publishes a $500 early move-in penalty. What a certificate is, which North Texas cities issue one for a house, how a temporary certificate works, and why your lender's completion test is a separate question entirely.
It depends entirely on the city, because Texas has no statewide certificate of occupancy. Some cities require one before a new dwelling may be occupied. Others do not issue them for houses at all — Plano's own guide says certificates "are not issued for single-family homes." Your lender's completion requirement is a separate matter.
That is an uncomfortable answer, so it is worth being precise about it. "We're waiting on the CO" is one of the most common sentences in the last two weeks of a new build, and in some North Texas cities there is no CO on a single-family house to wait for. Knowing which kind of city you are buying in changes what you should actually be asking.
What is a certificate of occupancy?
It is the city's written confirmation that a building may be occupied, issued by the building official once the inspections tied to the permit have passed. Texas cities adopt their building codes locally, by ordinance, with their own amendments. That local adoption is why the answer is not uniform across the Dallas–Fort Worth metroplex, let alone the state.
The City of Corpus Christi's development services department states the general code rule plainly in its own information bulletin on the subject, dated 23 January 2024: under the adopted International Residential Code, no dwelling or habitable space is to be used or occupied until the building official has issued a certificate of occupancy. The same bulletin notes two useful distinctions — a certificate is not required again when only ownership changes on a dwelling that already has one, and a remodel is closed out with a certificate of completion rather than a certificate of occupancy.
Which North Texas cities issue one for a new house?
This is where it gets specific, and where a general article is no substitute for the city's own answer. Three published positions, each from the city itself:
| City | What the city's own published material says |
|---|---|
| Plano | Its Certificate of Occupancy Guide, dated 3/2/2026, says a certificate "is required to occupy any building or property with nonresidential or multifamily uses," and, under where one is not required, that certificates "are not issued for single-family homes, nor farms." |
| Dallas | Its certificate of occupancy page quotes the city's development code as applying "except for single family and duplex uses." The same page nonetheless lists a residential temporary certificate of occupancy fee for one- and two-family dwellings at $250, an extension at $125, and an early move-in penalty at $500. |
| Corpus Christi | Its Information Bulletin 018, dated 23 January 2024, lists "residential construction of a new dwelling or habitable space to be occupied" among the cases where a certificate is obtained. |
Two things follow from that table.
First, a city that does not issue a certificate for a house has not thereby stopped caring when you move in. Dallas publishing an early move-in penalty of $500 alongside an exception for single-family uses is a reminder that occupancy timing is governed by more than one instrument, and that the absence of a certificate is not the absence of a rule.
Second, the reliable answer is address-specific. A builder working across several cities deals with several different closeout processes, and the one that applies to your house is the one in the city that issued its permit.
Does the code edition the city adopted matter?
Yes, because the adopted code is what sets the inspections the builder has to pass before anything gets signed off.
Frisco publishes its adopted codes, which include the 2024 International Residential Code, with amendments, effective 03-01-2026, along with the 2024 International Building Code, International Plumbing Code, International Mechanical Code and International Fuel Gas Code on the same effective date, and the 2023 National Electrical Code with amendments effective 02-16-2024.
The phrase "with amendments" is the part to notice. Two neighbouring cities can both adopt the 2024 IRC and still run different inspection lists, because each one amends it locally. That is also why a code edition adopted in March 2026 can govern a house that broke ground later that year.
Can you get a temporary certificate of occupancy?
In cities that issue one, yes — and it is a documented process, not a favour.
Corpus Christi's bulletin sets out the shape of it: a temporary certificate may be issued when all necessary permits have been obtained, all inspections preceding the final inspections are approved, and all outstanding fees are paid. The permit holder requests it from the appropriate inspector, who documents the approval and indicates the duration. The application asks for the requested occupancy date, the anticipated completion date for the permanent certificate, the areas requested and the reason. It holds until the permanent certificate issues or the temporary one expires, and an extension requires a fresh application and a fee.
Dallas publishes residential temporary certificate fees, listed in the table above, but its page does not set out the residential process, duration or conditions. Plano's two published certificate documents do not address temporary certificates at all. Duration and conditions are city-specific, so the only dependable source is that city's building inspections office.
What does the city's certificate have to do with your loan?
Less than most buyers assume, which is the point worth taking away.
For a conventional loan sold to Fannie Mae, the Selling Guide's section on verifying completion (B4-1.2-05, version dated 10 December 2025) requires verification that construction is complete before the loan is sold. The certificate of occupancy is not named in that section as evidence of completion — the documents that satisfy it are the appraiser's Form 1004D or a borrower-and-builder letter with photographs. The occupancy permit appears in that section exactly once, and in a different role: as a condition on what work may be left unfinished. Where a loan closes with minor items outstanding under the postponed-improvements policy, that work must not affect the ability to obtain an occupancy permit.
So the two approvals touch at one hinge, not along their whole length. The city decides whether the house may be occupied. The lender decides whether the house counts as complete. A house can satisfy one test and not yet the other, and the two are signed off by different people on different days.
That lender-side documentation — what Form 1004D is, what the borrower-and-builder letter must contain, and the limits on closing with work outstanding — is covered in its own article on this site about how an appraiser values a custom home that has not been built yet.
What should you be asking, and of whom?
Three questions, each aimed at the party that can actually answer it:
- To the city that issued the permit, for your specific address: does this city issue a certificate of occupancy for a single-family home? If yes, what remains on the inspection list, and is a temporary certificate available? If no, what marks the permit closed out?
- To your lender: which document will be used to verify completion, and who orders it? That ordering step is a routine source of a late delay that nobody has claimed.
- To your builder, in writing: if anything will be unfinished on closing day, what is it, what is it priced at, and is it in the contract?
None of that calls for a legal opinion. It calls for knowing that the city and the lender are asking different questions, and getting each answer from the party whose question it is.
What does this article not cover?
It does not cover every city. The three cities quoted above are published examples of three different positions, not a survey of the metroplex, and a city can change its position by ordinance. Fees, code adoptions and lender guidelines all change, so the ones that govern your purchase are the ones in force in your city on your closing date.
It is also not advice on your transaction. Where a question is about what a contract obliges you or your builder to do, or about the tax treatment of anything described here, it belongs with an attorney or a CPA. What belongs with the city is the occupancy question, and what belongs with your lender is the completion question.
Keep reading
Market figures are sourced as noted and reflect the period described. Information deemed reliable but not guaranteed.
More from the journal
Buying · November 19, 2026
How does an appraiser value a custom home that has not been built yet?
An appraiser values an unbuilt custom home from its plans and specifications, on a stated hypothetical condition that the home is already finished. What HUD's 90 percent threshold changes, what Fannie Mae accepts as a basis besides a plan set, who confirms the house got built as appraised on Form 1004D or a borrower-and-builder letter, and the four limits on closing before the last of the work is done.
Buying · November 18, 2026
What is the new Texas seller's water disclosure, and when do you get it?
Since 1 July 2026, Paragraph 7I of the TREC resale contract puts water rights on the face of the contract as a single checkbox with three settings. What the paragraph says, what TREC Form 61-0 asks the seller, which box carries a termination right, and the five statements that let a seller skip the disclosure entirely.
Buying · November 17, 2026
What are rollback taxes in Texas, and who pays them when agricultural land becomes a homesite?
A rollback tax is the additional tax charged when land appraised on its agricultural productivity is converted to a non-agricultural use. It covers the three tax years before the change of use, and the owner who changes the use owes it — which on an acreage purchase is often the buyer who builds, not the seller who sold.
Working through this yourself? The buyer's guide and the seller's guide cover the process end to end, and the communities pages set out each area in detail. Moving in from out of state? Start with relocating to Dallas–Fort Worth.