Can a subcontractor put a lien on your house if your builder does not pay them?
November 14, 2026 · By Kenny Agbim · 12 min read
Yes — a subcontractor you never hired can file a lien against your home. Texas Property Code Chapter 53 allows it, but only where strict notice and filing deadlines are met. On a homestead the conditions are tighter still: a written contract, executed before work began, signed by both spouses, and filed with the county clerk.
Can a subcontractor put a lien on your house if your builder does not pay them?
Yes — a subcontractor you never hired can file a lien against your home. Texas Property Code Chapter 53 allows it, but only where strict notice and filing deadlines are met. On a homestead the conditions are tighter still: a written contract, executed before work began, signed by both spouses, and filed with the county clerk.
That is the short answer, and it surprises most people building or remodelling. The plumber's supplier never signed anything with you. You paid your builder in full and on time. And a lien can still appear in the real property records against your address, because the right it rests on comes from the statute rather than from any agreement with you.
Chapter 53 also sets out the conditions that make such a lien invalid, and several of them are conditions on the owner's side of the build. This page walks through the mechanism in the order it actually happens.
Who is allowed to claim a lien on your house?
Two categories, and the difference between them runs through the whole chapter.
An original contractor is the person who contracted with you directly — the builder or the remodeller whose name is on your contract.
A derivative claimant is everyone behind them: subcontractors, their subcontractors, material suppliers, and the people who fabricate materials to order for your job. They have no contract with you. Section 53.102 describes what the reserved funds discussed below secure — payment to artisans and mechanics who perform labour, and to others who furnish material, or material and labour, or specially fabricated material for a contractor, subcontractor, agent or receiver.
The practical consequence: the people who can place a lien on your home are mostly people you have never met and whose names may not appear anywhere in your paperwork. Heading 6 of the statutory disclosure statement described below is "GET A LIST OF SUBCONTRACTORS AND SUPPLIERS," which is the legislature's own view of what to do about that.
What makes a lien on a Texas homestead different?
Section 53.254 adds requirements that apply to no other property, and they are the requirements most often missed.
| Subsection | What it requires |
|---|---|
| §53.254(a) | A written contract between the owner and the person who will furnish material or perform labour, setting out the terms |
| §53.254(b) | That contract must be executed "before the material is furnished or the labor is performed" |
| §53.254(c) | If the owner is married, the contract "must be signed by both spouses" |
| §53.254(e) | The contract must be filed with the county clerk of the county where the homestead is located, and the clerk records it |
| §53.254(f) | A homestead lien affidavit must carry, conspicuously at the top of the page and in at least 10-point boldface, the notice: "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN." |
| §53.254(g) | For the lien to be valid, the notice given to the owner under Subchapter C must include or attach a statement about subcontractor non-payment |
Three things are worth drawing out.
The timing in (b) is absolute. A contract signed after the first delivery of material does not satisfy the subsection. Papering it later does not cure it.
Both spouses, in (c). Not the spouse on the deed. Both.
Section 53.254(d) provides that a contract made by an original contractor benefits all persons who labour or furnish material for that contractor. So the single contract you sign with your builder is the document the whole chain behind them relies on. If it does not meet (a), (b), (c) and (e), that defect runs down the chain.
What are you supposed to receive before you sign a residential construction contract?
A disclosure statement, and Section 53.255(a) puts the deadline before your signature: "Before a residential construction contract is executed by the owner," the original contractor shall deliver it to the owner.
Section 53.255(b) requires the statement to read substantially similar to the text set out in the statute. Rather than reproduce it, here are its twelve headings in order, because the headings alone tell you what the legislature thinks a homeowner needs to know:
- KNOW YOUR RIGHTS AND RESPONSIBILITIES UNDER THE LAW
- CONVEYANCE TO CONTRACTOR NOT REQUIRED
- KNOW YOUR CONTRACTOR
- GET IT IN WRITING
- READ BEFORE YOU SIGN
- GET A LIST OF SUBCONTRACTORS AND SUPPLIERS
- MONITOR THE WORK
- MONITOR PAYMENTS
- CLAIMS BY SUBCONTRACTORS AND SUPPLIERS
- SOME CLAIMS MAY NOT BE VALID
- OBTAIN A LIEN RELEASE AND A BILLS-PAID AFFIDAVIT
- OBTAIN TITLE INSURANCE PROTECTION
Heading 2 is there for a reason. Some arrangements ask a homeowner to convey the lot to the builder during construction, and the statute tells the owner plainly that this is not required of them.
Headings 11 and 12 are about the end of the build rather than the beginning, and they are the two that close this risk out.
What happens if the contractor never gave you that statement?
Nothing, to the lien. Section 53.255(c) is explicit that a contractor's failure to comply with the section "does not invalidate a lien under this chapter, a contract lien, or a deed of trust."
This is the part people get wrong in both directions. The disclosure statement is required, and a contractor who skips it has not followed the statute. But its absence is not a defence against a subcontractor's lien, and it does not void anything. The grounds that do invalidate a lien are in Section 53.160, below.
What is the 10 percent you are supposed to hold back?
Statutory retainage, under Section 53.101 — and it is an obligation on the owner, not an option.
During the progress of work under an original contract for which a mechanic's lien may be claimed, and for 30 days after the work under the contract is completed, the owner must reserve either:
- 10 percent of the contract price of the work to the owner, or
- 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done — using the contract price, or the reasonable value if there is no contract price.
Section 53.102 then makes those reserved funds security for the people down the chain.
Why it matters to you: the statement required by Section 53.254(g) warns the owner that a subcontractor's or supplier's lien can attach where the owner failed to withhold enough to cover an unpaid claim after receiving notice of it, or failed to reserve the 10 percent during construction and for 30 days after completion. Read the other way round, the same statement says that where the owner has complied, a lien by a subcontractor who did not contract directly with the owner is not valid, and the owner is not liable for payments made before notice beyond that 10 percent reserve.
So the 10 percent is not a bargaining chip held back from a builder. It is the thing that caps your exposure to people you never hired. Heading 9 of the disclosure statement, "CLAIMS BY SUBCONTRACTORS AND SUPPLIERS," carries the same 10 percent reserve, held for 30 days after final completion, termination or abandonment.
How retainage is handled in practice on a particular build is a question for the attorney and the title company who prepare and close the loan and lien documents, and for the lender disbursing against the work. It is not an agent's call and this page does not tell you how to set it up.
When does a subcontractor have to tell you they have not been paid?
Before they can hold a valid lien. Section 53.056 requires a claimant other than an original contractor to send a notice of claim for unpaid labour or materials to the owner or reputed owner and to the original contractor, and residential projects run on a shorter clock than everything else.
| Deadline under §53.056(a-1) | Residential construction project | Other projects |
|---|---|---|
| Notice of claim to owner and original contractor | Not later than the 15th day of the second month after the month during which the trigger occurred | Not later than the 15th day of the third month |
The triggering month is the month in which the labour or materials were provided, or in which undelivered specially fabricated materials would normally have been delivered. Section 53.057 sets a separate notice regime for a retainage claim.
That notice is the moment the chapter hands you information and a decision at the same time. It is also the moment that, under the Section 53.254(g) statement, starts mattering to what you withhold.
When does the lien affidavit have to be filed?
Residential projects again run a month shorter. Section 53.052 sets the deadlines; Section 53.054 sets out what the affidavit must contain.
| Who is filing | Residential construction project | Other projects |
|---|---|---|
| Original contractor — §53.052(a) | Not later than the 15th day of the third month after the month in which the work was completed, terminated or abandoned | 15th day of the fourth month |
| Derivative claimant — §53.052(c) and (b) | Not later than the 15th day of the third month after the later of the month it last provided labour or materials, or the specially fabricated delivery month | 15th day of the fourth month |
Under Section 53.054(a), the affidavit must be signed and must state the sworn amount of the claim, the owner's name and last known address, a general description of the work and materials, who employed the claimant or who it supplied, the original contractor's name and address, a legally sufficient property description, and the claimant's own name and addresses. A claimant who is not the original contractor must also state the date each owner notice was sent and the method used.
That last item is not a formality. It is the point at which a missed notice becomes visible on the face of the affidavit.
How does an invalid lien get removed?
Section 53.160 provides a summary motion in a suit to declare a lien invalid or unenforceable, and subsection (b) limits the grounds to seven. Three of them are specific to homestead property.
| Ground in §53.160(b) | In plain terms |
|---|---|
| (1) | The notice of claim was not timely furnished under §53.056 or §53.057 |
| (2) | The lien affidavit failed to comply with §53.054, or was not filed as required by §53.052 |
| (3) | Notice of the filed affidavit was not furnished under §53.055 |
| (4) | The retainage-claim deadlines expired, and the owner complied with §53.101 and paid out before the claim was perfected and before notice |
| (5) | All funds subject to the notice were deposited in the court registry and the owner has no further liability |
| (6)(A) | Homestead: "no contract was executed or filed as required by Section 53.254" |
| (6)(B) | Homestead: the affidavit lacked the §53.254 notice |
| (6)(C) | Homestead: the notice of claim lacked the §53.254 statement |
| (7) | The claimant signed a valid and enforceable waiver or release of the claim or lien |
Two procedural points from the same section. Under subsection (c), the claimant must be given at least 30 days' notice before the hearing on the motion. Under subsection (d), on grounds (1) and (3) the burden is on the claimant to prove the notices were furnished — not on the owner to prove they were not.
Ground (4) is the one that connects back to the 10 percent: it is available only where the owner complied with Section 53.101. The other six grounds turn on the claimant's own notices, filings and releases rather than on anything the owner did, so they are unaffected either way.
Whether any of this applies to a particular lien is a question of law on particular facts, and it belongs with an attorney. This page describes what the chapter says, not what any lien means.
Who actually does what at the end of a build
- The original contractor delivers the §53.255 disclosure statement before you sign, and signs the written contract that §53.254 requires.
- The owner reserves the 10 percent under §53.101 and holds it for the 30 days after completion.
- Subcontractors and suppliers send the §53.056 notice if they are unpaid, and file under §53.052 within the deadline.
- The title company is where headings 11 and 12 of the disclosure statement land — the lien release, the bills-paid affidavit, and the title insurance coverage that addresses this risk at closing.
- An attorney prepares and interprets the lien documents, advises on retainage in your particular contract, and handles any claim that arrives.
- Your agent holds the timeline and makes sure these questions get asked of the right people before the contract is signed rather than after the keys are handed over. None of these decisions is an agent's to make.
What this page does not establish
- Whether the text read for this page is the current law. The official host carries no "current through" header. Its newest amendment credit in Chapter 53 is Senate Bill 929 of the 89th Legislature, effective 21 May 2025. Any amendment after that date is not reflected and was not checked.
- The constitutional layer. Article XVI, Section 50 of the Texas Constitution also bears on liens against a Texas homestead. That text was reached on the official host for this page but is not quoted, paraphrased or relied on here, and nothing above should be read as a statement of what it requires.
- Section 53.001, the definitions. Not read for this page. "Residential construction project," "completion" and other terms used above are defined terms, and the definition may be narrower than the ordinary meaning.
- Constitutional and contractual liens. Chapter 53 is one of several routes to a lien. The others are not described here.
- Anything about a specific lien. No deadline, ground or percentage above is a conclusion about any actual claim.
Sources read 14 November 2026
- Texas Property Code, Chapter 53 (Mechanic's, Contractor's, or Materialman's Lien) — official text, read in full at https://tcss.legis.texas.gov/resources/PR/htm/PR.53.htm and cross-read at https://tcss.legis.texas.gov/resources/PR/pdf/PR.53.pdf. Source of every section, deadline and percentage on this page: §§53.052, 53.054, 53.055, 53.056, 53.057, 53.101, 53.102, 53.160, 53.254 and 53.255. Amendment credits on the sections used are Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), effective 1 January 2022, except §53.054, whose latest credit is Acts 1997, 75th Leg., ch. 526, effective 1 September 1997. The chapter's newest credit overall is Acts 2025, 89th Leg., R.S., Ch. 98 (S.B. 929), effective 21 May 2025, at §§53.003 and 53.124. No currency header appears on either file.
- statutes.capitol.texas.gov — attempted for the same chapter in both HTM and PDF. Returned the site's navigation shell with no statutory text, as it has on every run since 16 October 2026. No text was taken from it.
- Porter Hedges, "Construction Law Update from the 89th Texas Legislature Regular Session," 29 May 2025 — read only to cross-check the 2025 amendment. It reports S.B. 929 as a clarification to §53.003(e) on weekend and holiday deadline extensions, signed and effective 21 May 2025. The post predates the end of that session and does not mention §53.124, which the statute text shows S.B. 929 also amended.
Statutes are amended. Every section, deadline and figure above should be checked against the current official text before it is relied on.
Kenny Agbim is a REALTOR® with eXp Realty LLC in Dallas–Fort Worth, Texas licence 820897. This article explains what a published statute says. It is not legal advice, it is not tax advice, and Dreams 2 Doorsteps is a real estate brokerage practice, not a law firm. Nothing here drafts, interprets or alters any contract or promulgated form, and a question about the legal effect of a document or a claim belongs with your own attorney.
Keep reading
Market figures are sourced as noted and reflect the period described. Information deemed reliable but not guaranteed.
More from the journal
Buying · November 20, 2026
Do you need a certificate of occupancy to close on a new home in Texas?
Texas has no statewide certificate of occupancy, so the answer is set city by city. Plano's own guide says certificates are not issued for single-family homes. Dallas's development code applies except for single family and duplex uses, yet the city still publishes a $500 early move-in penalty. What a certificate is, which North Texas cities issue one for a house, how a temporary certificate works, and why your lender's completion test is a separate question entirely.
Buying · November 19, 2026
How does an appraiser value a custom home that has not been built yet?
An appraiser values an unbuilt custom home from its plans and specifications, on a stated hypothetical condition that the home is already finished. What HUD's 90 percent threshold changes, what Fannie Mae accepts as a basis besides a plan set, who confirms the house got built as appraised on Form 1004D or a borrower-and-builder letter, and the four limits on closing before the last of the work is done.
Buying · November 18, 2026
What is the new Texas seller's water disclosure, and when do you get it?
Since 1 July 2026, Paragraph 7I of the TREC resale contract puts water rights on the face of the contract as a single checkbox with three settings. What the paragraph says, what TREC Form 61-0 asks the seller, which box carries a termination right, and the five statements that let a seller skip the disclosure entirely.
Working through this yourself? The buyer's guide and the seller's guide cover the process end to end, and the communities pages set out each area in detail. Moving in from out of state? Start with relocating to Dallas–Fort Worth.